The Energy Regulatory Office of Kosovo has partially approved the revenue requests of operators in this sector, aiming to avoid an increase in electricity prices.
As a result, the maximum allowed revenues for the Transmission System Operator (KOSTT) will be €76 million, for the Distribution System Operator (KEDS) €185 million, and for the Universal Service Supplier (KESCO) €442 million.
Muharrem Gashi from the Department of Tariffs and Prices justified the decision by saying that, with increased imports, the maximum allowed revenues need to be adjusted.
Lokaj stated that, following comments received from the Distribution System Operator, ERO updated loss purchases based on actual data from March 2026 and revised the assumed import price for the remaining months of April–December 2026 to €2.65/MWh.
For KESCO, Gashi added that the main cost component remains electricity procurement for supplying consumers.