B-2 unit revision completes successfully 
Read in: 1 min.
3 year ago
Link copied

The Energy Corporation of Kosovo has announced that the revision of the B-2 unit has been successfully completed.

KEK, through an announcement, said that thanks to the organization of the management and the maximum commitment of the KEK workers, it was possible to successfully complete all the planned works according to the revision plan of unit B-2 in Power station Kosova B.

"Furthermore, unit B - 2 completed the revision (planned 8 days) 3 days earlier and returned to operation on date. 12.11.2022 at 21:40", the announcement states.

This web site is maintained and managed by News Agency KosovaPress. All material on this site is unique production of KosovaPress, thus KosovaPress holds all the rights provided by copyright law according to legal dispositions on copyright and intellectual property. Use, modification and distribution for commercial purposes are strictly forbidden.
This website application was developed with the support of #SustainMedia Programme, co-funded by the European Union and the German Government, implemented by GIZ, DW Akademie and Internews. Its contents are the sole responsibility of KosovaPress and do not necessarily reflect the views of the EU or the German Government.
A.P.L. KosovaPress © 2002-2026 All rights reserved