B-2 unit revision completes successfully 

B-2 unit revision completes successfully 

The Energy Corporation of Kosovo has announced that the revision of the B-2 unit has been successfully completed.

KEK, through an announcement, said that thanks to the organization of the management and the maximum commitment of the KEK workers, it was possible to successfully complete all the planned works according to the revision plan of unit B-2 in Power station Kosova B.

“Furthermore, unit B – 2 completed the revision (planned 8 days) 3 days earlier and returned to operation on date. 12.11.2022 at 21:40”, the announcement states.